The first concrete pour is in and more are soon to follow as the construction site begins to hum with activity. The initial pour was for the foundation of…
-
Construction is moving forward at a brisk pace at the site of Valley Public Radio's new home at the Research and Technology Park in Clovis at Temperance &…
-
Valley Public Radio listeners Eric & Yvonne Pennestri of Porterville sent us their own pictures of construction on Valley Public Radio's new building.…
-
Over the past two weeks workers have hauled tons of fill dirt to the site to raise the grade several inches, in preparation for pouring the foundation's…
-
The job site is a busy place these days as work crews are busy doing site excavation and grading for the foundation of our new building. Work crews are in…
-
On Tuesday May 19th, Valley Public Radio broke ground on construction a new broadcast center, which will serve the station and the San Joaquin Valley for…
-
Shortly before Valley Public Radio's official groundbreaking ceremony on Tuesday, construction crews began breaking some ground of their own on the $4.5…
-
Workers began the first actual construction activities at the site today, with saw cuts to take up the existing asphalt in what today is a parking lot.…
-
The design-build crew met at the construction site today to go over plans for the groundbreaking ceremony next Tuesday and to discuss construction…
-
Site preparation is already underway at our parcel on Alluvial and Temperance in Clovis. Today the project's general contractor Zumwalt Construction…